The BBRS issues a Specialty CSL for roof covering: construction, reconstruction, alteration, repair, or removal of roof covering, including replacement of up to 25% of sheathing and sistering up to 25% of roof rafters, on buildings under 35,000 cubic feet, 1- and 2-family dwellings, and agricultural buildings. OCABR's job chart lists new or replacement roofing as requiring a CSL ('Roofing CSL minimum'), HIC registration, and a building permit; minor repairs need a CSL and HIC registration and a permit unless the building official deems them ordinary repairs.
Specialty CSL holders complete six hours of continuing education every two years and renew for $100. The contractor signing with an owner-occupant must also be HIC-registered ($150 plus a $100–$500 Guaranty Fund payment) and use a written contract for any job over $1,000.
The state sets the license floor; the county or city permit office controls filing, inspections, and local rules wherever the job site sits.
780 CMR is a single statewide building code (M.G.L. c. 143, § 94); local building commissioners enforce it, issue permits, and record the supervising CSL holder and HIC registration on each permit. Municipalities may also adopt DOER's stretch or specialized energy codes (225 CMR 22.00/23.00), so check the town before pricing energy work. There is no separate local contractor license for building work in the state framework, but the BBRS advises checking with the local building official for additional requirements.
The local offices section below names the exact permit desk for every Massachusetts county on file.
Each row names the issuing authority, cost, timeline, citation, and status behind the requirement — verified against the official source.
Published fees from the issuing authorities, as of October 2026. Local permit fees vary by project and jurisdiction — the basis is stated where a flat number does not exist.
The roof covering specialty CSL includes replacing up to 25% of sheathing and sistering up to 25% of roof rafters; beyond that, a broader CSL is needed.
Minor roof repairs may skip the permit if the building official considers them ordinary repairs — the CSL and HIC requirements on OCABR's chart still apply.
Guaranty Fund eligibility requires that the contractor — not the homeowner — secured the building permit.
A practical sequence for a new roofing contractor in Massachusetts. Actual agency processing times are noted in the ledger above.
Each item names the issuing authority, cycle, and citation.
Statutory consequences with their citations — not estimates, not “commonly cited” guesses.
Knowingly, willfully, or negligently performing residential contracting on an owner-occupied 1–4 unit home without a certificate of registration — or after it lapses, is suspended, or is revoked.
Supervising regulated construction without the required CSL violates 780 CMR, which is the state building code; practice on an expired CSL is expressly prohibited (780 CMR 110.R5.2.5).
Inside city limits, the city office listed here issues the permit; the county office serves unincorporated areas. Every office links to its official page.
| County · City | Permit office | Portal |
|---|---|---|
| Hampden County Springfield (consolidated gov.) | City of Springfield Department of Code Enforcement — Building Division ↗ | Springfield Building Permit Lookups (OpenGov) ↗ |
| Suffolk County Boston (consolidated gov.) | City of Boston Inspectional Services Department (ISD) ↗ | ISD Online Permits and Licenses ↗ |
Every fact in this file was checked against these official sources on October 2026.
Pending verification: Initial CSL license fee and PSI exam fee — mass.gov lists only the $100 renewal fee; c. 142A, § 11 ties the HIC fee to the CSL fee, which suggests but does not confirm a $150 initial CSL fee · Statutory or regulatory source of the $25,000 Guaranty Fund cap shown on OCABR's pages (c. 142A, § 6 as retrieved states no dollar cap; the change date was not found) · OCABR's HIC/CSL/permit job chart is labeled 'general guidance only'; the building official decides whether a specific job needs a permit or CSL
General information, not legal advice. Always confirm requirements, deadlines, and forms with the issuing authority before filing or contracting.