SDCL 36-16-13 requires a State Electrical Commission license for anyone who, for pay, plans, lays out, supervises, installs, alters, or repairs wiring, apparatus, or equipment for electric light, heat, or power. Only a licensed electrical contractor may contract for electrical work; a Class B electrician (36 months' experience) may contract only for farm and residential wiring (SDCL 36-16-14). Apprentices register with the commission and work under personal supervision.
A journeyman needs four years (8,000 hours) as a licensed apprentice; an electrical contractor needs two more years as a journeyman — including 2,000 commercial hours — or one year of commercial work as a Class B. Contractors and Class B electricians deposit a $10,000 undertaking, $100,000/$300,000 public liability insurance, and a $50 deposit. Licenses run two years, expiring June 30 of even years, with 16 hours of CE per cycle; the commission inspects under the 2023 NEC as of November 12, 2024.
The state sets the license floor; the county or city permit office controls filing, inspections, and local rules wherever the job site sits.
Electrical licensing is statewide, and a licensed contractor or Class B electrician need not furnish an additional undertaking for a municipal license (SDCL 36-16-20). SDCL 36-16-35 lets municipalities, rural electric cooperatives, and utilities impose more stringent requirements, and the commission's rules provide for approved local inspection systems; outside those, the commission issues wiring permits and inspects.
The local offices section below names the exact permit desk for every South Dakota county on file.
Each row names the issuing authority, cost, timeline, citation, and status behind the requirement — verified against the official source.
Published fees from the issuing authorities, as of October 2026. Local permit fees vary by project and jurisdiction — the basis is stated where a flat number does not exist.
A Class B electrician may contract only for farm and residential wiring; everything else needs an electrical contractor (SDCL 36-16-14).
All licenses expire June 30 of each even-numbered year; the 2026 renewal window opened April 20, 2026 with CE certificates for July 1, 2024–June 30, 2026.
Owners wiring their own detached residence or farmstead need no license, but services over 60 amps and new circuits are inspected and fee-bearing (SDCL 36-16-15).
A practical sequence for a new electrical contractor in South Dakota. Actual agency processing times are noted in the ledger above.
Each item names the issuing authority, cycle, and citation.
Statutory consequences with their citations — not estimates, not “commonly cited” guesses.
Engaging in electrical contracting or performing licensed electrical work without a State Electrical Commission license, or failing to register or report wiring, is a crime; the commission may seek an injunction instead.
The commission may refuse, revoke, suspend, or limit a license for violating the law, rules, or the adopted National Electrical Code, or for knowingly aiding unlicensed work.
Inside city limits, the city office listed here issues the permit; the county office serves unincorporated areas. Every office links to its official page.
Every fact in this file was checked against these official sources on October 2026.
Pending verification: The actual examination fee charged by the commission's exam administrator (statute caps it at $150 per attempt) · Which cities currently run commission-approved local electrical inspection systems (e.g., Sioux Falls, Rapid City) and any local electrical licensing they add · Late renewal and reinstatement fees beyond the $50 reinstatement fee in ARSD 20:44:16:18
General information, not legal advice. Always confirm requirements, deadlines, and forms with the issuing authority before filing or contracting.
Store licenses, permits, policies, and renewal dates in one place.