No Wyoming statute licenses concrete, foundation, or flatwork contractors. Local contractor licensing applies where a city or county has adopted it, and W.S. 16-6-1101 requires Wyoming jurisdictions to honor each other's licenses when the contractor shows a passing ICC or equivalent exam. Building permits and inspections for foundations and structural concrete come from jurisdictions holding delegated code authority (W.S. 35-9-121).
Statewide, concrete work is construction and therefore extrahazardous employment: an employer may not start work without a workers' compensation statement of coverage from the Department of Workforce Services (W.S. 27-14-108, 27-14-207). To keep lien rights, a prime contractor must send the owner a preliminary notice before taking any payment, and a sub within 30 days of first work (W.S. 29-2-112). On public concrete work, a DWS-certified resident contractor gets a 5% bid preference (W.S. 16-6-102).
The state sets the license floor; the county or city permit office controls filing, inspections, and local rules wherever the job site sits.
Wyoming has no statewide license for this trade, so contractor licensing is local. Cities, towns, and counties that license contractors set their own classes, exams, and bonds, but W.S. 16-6-1101 requires each of them to recognize an active, good-standing license issued by another Wyoming jurisdiction when the contractor shows a passing International Code Council (or equivalent) exam — with no retesting, though the accepting jurisdiction may require its own proof of financial assurance. Building codes are enforced by municipalities and counties that have taken delegated authority from the State Fire Marshal (W.S. 35-9-121), and any electrical work stays with state-licensed electrical contractors (W.S. 35-9-123).
The local offices section below names the exact permit desk for every Wyoming county on file.
Each row names the issuing authority, cost, timeline, citation, and status behind the requirement — verified against the official source.
Published fees from the issuing authorities, as of October 2026. Local permit fees vary by project and jurisdiction — the basis is stated where a flat number does not exist.
Wyoming issues no state license for this trade; the license you need, if any, comes from the city or county where the job is.
Another Wyoming jurisdiction must recognize your local license without retesting if you show a passing ICC or equivalent exam (W.S. 16-6-1101(b)(ii)).
Primes file a lien statement within 150 days and others within 120 days of the last work or substantial completion, after a 20-day notice of intent (W.S. 29-2-106, 29-2-107).
A practical sequence for a new concrete contractor in Wyoming. Actual agency processing times are noted in the ledger above.
Each item names the issuing authority, cycle, and citation.
Statutory consequences with their citations — not estimates, not “commonly cited” guesses.
A contractor, subcontractor, or materialman who does not send the preliminary notice within the time required loses the right to assert a construction lien.
An employer that does not apply for coverage is liable to the state for every award paid and reserved for an injured employee; unpaid premiums carry interest.
Installing electrical equipment without being, or employing, a licensed electrical contractor violates the electrical act.
Inside city limits, the city office listed here issues the permit; the county office serves unincorporated areas. Every office links to its official page.
| County · City | Permit office | Portal |
|---|---|---|
| Laramie County Cheyenne | City of Cheyenne Building Permitting & Licensing Division (Building Safety) ↗ Unincorporated: Laramie County Planning & Development — Building Department ↗ | City of Cheyenne OpenGov Portal ↗ |
Every fact in this file was checked against these official sources on October 2026.
Pending verification: Local contractor licensing classes, exams, bonds, and fees in Cheyenne / Laramie County, Casper, Gillette, and other Wyoming cities and counties (local programs, outside this state-level record) · 2024–2026 session laws were not reviewed bill by bill (the wyoleg.gov bill-information service timed out); statute text was read from the Title PDFs compiled May 8, 2026
General information, not legal advice. Always confirm requirements, deadlines, and forms with the issuing authority before filing or contracting.
Store licenses, permits, policies, and renewal dates in one place.