HomeGeorgiaElectrical
ELECTRICAL x GEORGIA

Electrical contractor requirements in Georgia.

Georgia's electrical license is a contractor credential from the Division of Electrical Contractors of the State Construction Industry Licensing Board: there is no state journeyman electrician card. Class I is restricted to single-phase installations of 200 amperes or less; Class II is unrestricted.

Both classes require four years of primary experience and a PSI exam (70 to pass). Note for anyone relying on older guides: Georgia ended electrical licensure by reciprocity effective May 2026.

STATE LICENSE
RequiredGeorgia State Board of Electrical Contrac…
STATUTE
O.C.G.A. Title 43, Chapter 14
RENEWAL
Biennial — June 30, even years4 hrs / yr (8 per cycle)
VERIFIED
September 2026Official sources
FILE · ELECTRICAL x GEORGIA
Compliance Dossier
Public
File
September 2026
STATE AUTHORITYGeorgia State Board of Electrical Contractors (State Construction Industry Licensing Board)
STATUTE / CODEO.C.G.A. Title 43, Chapter 14
SCOPEStatewide · Georgia
RENEWALBiennial — June 30, even years
CONTINUING ED.4 hrs / yr (8 per cycle)
LOCAL OFFICES9 counties on file
FILE ELECTRICALSCOPE STATEWIDE · GEORGIATYPE VERIFIED RULE FILE
VERIFIED September 2026STATUS PUBLIC REFERENCE
What this file settlesThe Georgia rules for electrical contractors, verified against official sources.
LICENSE TRUTH
Electrical contracting in Georgia requires a statewide Class I or Class II Electrical Contractor license from the Board of Electrical Contractors — the board licenses contractors, not individual electricians.
STATE ↔ LOCAL
The license is expressly statewide; local governments issue the per-job electrical permits and inspections and require the state license to pull them. Statutory exemptions in § 43-14-13(i) cover irrigation wiring and low-voltage lighting (separate low-voltage licensing).
EVERY CLAIM SOURCED
Each requirement below carries its citation and official source. Facts we could not confirm are listed as pending — never asserted.
§ 01 · Permit Stack

How electrical work is governed in Georgia.

The state sets the license floor; the county or city permit office controls filing, inspections, and local rules wherever the job site sits.

STATE — THE LICENSE
Board of Electrical Contractors
CLASS I OR II LICENSE4 YRS EXPERIENCEPSI EXAM
COUNTY — OVERLAY
County offices
OCCUPATION TAX CERT
LOCAL — WHERE YOU FILE
City / county permit office
ELECTRICAL PERMITSINSPECTIONS

Read it bottom-up.

The license is expressly statewide; local governments issue the per-job electrical permits and inspections and require the state license to pull them. Statutory exemptions in § 43-14-13(i) cover irrigation wiring and low-voltage lighting (separate low-voltage licensing).

The local offices section below names the exact permit desk for every Georgia county on file.

Source · Georgia State Board of Electrical Contractors (State Construction Industry Licensing Board)Last verified · September 2026
§ 02 · Specs Ledger

Every requirement, with a number on it.

Each row names the issuing authority, cost, timeline, citation, and status behind the requirement — verified against the official source.

RequirementIssued byCostTimeCitationStatus
Electrical Contractor LicenseCompany-level credential, Class I or II
GA SoS / CILB
$110 application
Exam via PSI
O.C.G.A. § 43-14-8
REQUIRED
Biennial RenewalExpires June 30 of even-numbered years
GA SoS
$75 ($100 late)
Every 2 years
CILB fee schedule
REQUIRED
Continuing EducationApproved providers, tracked in CE Broker
Board-approved providers
4 hrs / yr
Annual
Board rule 121-4-.07
REQUIRED
Electrical PermitsPer job, at the local office for the site
City / county
By valuation
Per project
Local code
REQUIRED
Workers' CompensationWith 3 or more employees
Private carrier
Premium by payroll
Before hiring
O.C.G.A. § 34-9-2
CONDITIONAL
Occupation Tax CertificateLocal business license where based
County / city
Set by locality
Annual
Local code
REQUIRED
§ 03 · Year-One Cost

What it costs to start electrical in Georgia.

Published fees from the issuing authorities, as of September 2026. Local permit fees vary by project and jurisdiction — the basis is stated where a flat number does not exist.

Year-one ledger
Georgia · Electrical
License applicationVia GOALS portal$110
PSI examFee set at PSI registration, not publishedSet by PSI
RenewalBiennial; $100 late, $150 lapsed$75
CE courses4 hrs/yr, approved providersProvider rate
License verificationIf another state asks$35
Year-one floor$185+ in state fees + exam/CE
Excludes tools, vehicle purchase, payroll, and marketing.
NOTE
No individual electrician license

Georgia licenses the electrical contractor, not journeyman electricians — crews work under the licensed contractor.

NOTE
Reciprocity ended

Licensure by reciprocity (formerly AL, LA, NC, SC, TN) is no longer offered as of May 2026 — everyone takes the Georgia exam.

NOTE
No state insurance minimum

The board imposes no insurance or bond for licensure; local offices and customers still expect coverage.

§ 04 · Path to First Job

From day zero to first inspection.

A practical sequence for a new electrical contractor in Georgia. Actual agency processing times are noted in the ledger above.

1
STEP 1
Document 4 years' experience
Primary electrical experience
2
STEP 2
Apply via GOALS
GA SoS — $110
3
STEP 3
Pass the PSI exam
Score 70+
4
STEP 4
License issued
Electrical Board
5
STEP 5
Occupation tax certificate
County / city
6
STEP 6
Pull electrical permits
Local office per job
§ 05 · Compliance Checklist

Check them off.

Each item names the issuing authority, cycle, and citation.

01
Choose your class honestly
Class I stops at single-phase 200A service; document larger-system experience for Class II.
STATESCOPEBoard rules 121-2
CILBIssuing authority
02
Log 4 CE hours a year
8 hours per biennial cycle from approved providers, tracked in CE Broker.
RENEWALEDUCATIONBoard rule 121-4-.07
CE BrokerIssuing authority
03
Renew by June 30, even years
Late window follows; lapse escalates to reinstatement.
RENEWALDEADLINECILB fee schedule
GA SoSIssuing authority
04
Permit every job
Electrical permits and inspections run through the local office where the work sits.
PERMITLOCALLocal code
Local officeIssuing authority
05
Know the low-voltage carve-outs
Irrigation-system wiring and low-voltage lighting sit under separate low-voltage licensing, with statutory exemptions.
STATEADJACENTO.C.G.A. § 43-14-13(i)
CILBIssuing authority
§ 06 · Enforcement

What the law does about unlicensed electrical work.

Statutory consequences with their citations — not estimates, not “commonly cited” guesses.

§
O.C.G.A. Title 43, Ch. 14Statute

Unlicensed practice

Services may not legally be performed without an active license; the board publishes cease-and-desist orders against unlicensed practice.

ConsequenceCease-and-desist / board enforcement
§
Local codeStatute

Unpermitted work

Electrical work without local permits draws local enforcement regardless of licensure.

ConsequenceStop-work orders / fines
§
Board rulesStatute

Contract exposure

Unlicensed contracting undermines payment claims and invites board discipline on top of local enforcement.

ConsequenceBoard discipline
§ 07 · Local Offices

Where the permit is filed, county by county.

Inside city limits, the city office listed here issues the permit; the county office serves unincorporated areas. Every office links to its official page.

§ 08 · Georgia FAQ

Questions electrical contractors ask about Georgia.

Q01Do electricians need a license in Georgia?+
Georgia licenses electrical contractors, not individual electricians — anyone contracting for electrical work needs a Class I or Class II Electrical Contractor license; employees work under the licensee.
Q02What can a Class I contractor do?+
Single-phase installations up to 200 amperes at the service drop or lateral. Anything bigger — three-phase, heavier services — requires Class II.
Q03Can I transfer my out-of-state electrical license?+
Not anymore — Georgia ended electrical licensure by reciprocity effective May 2026. All applicants take the Georgia PSI exam.
Q04When does the license renew?+
Biennially, expiring June 30 of even-numbered years, with 4 CE hours required each year.
§ 09 · Sources

Primary authorities, not secondary summaries.

Every fact in this file was checked against these official sources on September 2026.

Pending verification: PSI exam fee (set at registration, not published officially) · Exact statutory penalty text and § 43-14-13 full text — official O.C.G.A. portal unreachable on the research date · Application-fee discrepancy: current GOALS guide says $110; the 2022 fee schedule PDF says $40

General information, not legal advice. Always confirm requirements, deadlines, and forms with the issuing authority before filing or contracting.

These are the documents Iris tracks for you.

Store licenses, permits, policies, and renewal dates in one place.